Precautions during work in track circuited area :-
• Level of ballast should be 50mm below the bottom of rail.
• The side drains, cross drains and the longitudinal drains if any should be well in gradient so as to drain out water quickly.
• The metal sleepers should not be used neighboring the insulated joints.
• The Burr formed at the end of rail at insulated joint should be scratched.
• There should be perfect insulation in fastening at insulated joints.
• The tools and equipments should not be placed at joints, else circuit may break.
• Packing under the insulated joint should be proper.
• Cutting of rail should be in the presence of S & T staff.
• The steel tape should not be used in track circuited sections.
• Gauge-cum-level equipment should be insulated.
• Push trolley should be insulated.
• Diplorry should not be put in track circuited sections without prior permission of S.M.
• Glued joint should be used in place of ordinary insulated joint.
• J-clips should be used in insulated joints.
• Bond wires should not be disturbed if it is disconnected during maintenance, it should be restored after the work.
• Pulling back of rails in track circuited area should be done in the presence of S & T staff.
• In track circuited area the cross pipes, G.I pipes, cables should be well under the rail.
• The ballast in track circuited section should be neat and clean.
• The P.Way staff should be aware of short circuiting, its reasons and measures to prevent it.
• The Ash pit, water column if any in existence should be well maintained in track circuited sections.